top of page
2019-06-04 g.jpg

Stormwater Bond Projects - Project Website

This is the project website for the Raytown Stormwater Bond Projects. We are currently completing the Final Designs for the selected project areas. To see the selected project areas, please click on the Selected Projects tab above. As the design develops, this site will be updated regularly, so please check back.

Thank you to everyone who joined us for the Open Houses held in 2024 to learn about the projects and to help set priorities.

  • We have evaluated the information gathered and made our selection of the stormwater improvement areas. Please click on the Selected Projects tab above to see this information.
  • Please note that this is an ongoing project, so report any flooding you have observed on the "Report Flooding Form." The more information we have, the better we can help address issues.
  • To see the flood levels in your area, visit the interactive "Flooding Map"
update

PROJECT UPDATE - August 25, 2026 

The first of the selected projects – Eastside Industrial Area - is approximately 80% complete. Infrastructure Solutions, LLC, was selected as the lowest bidder for the construction. They have been diligently working along Hadley Street, 65th Street, and Railroad Street to complete the project. Construction is projected to be completed by the end of September, weather permitting. The final phase of construction will be mill and overlay of the streets in the project area, as well as new concrete pavement on Railroad Street. This project is anticipated to finish under budget and ahead of schedule.

What’s next? 

  • The design team has finalized construction plans for the next priority area – Green Valley Subdivision. This project is anticipated to be released for bidding at the end of September, with construction starting in late Fall 2026. 

  • The design team is preparing final plans for the third priority area – a combination of Gregory Heights and 80th Terrace at Blue Ridge Blvd. These two neighborhoods will be bid and constructed together. Construction is anticipated to start in late Spring 2027.

Raytown's Stormwater System

40+ years old

$7.2 M

Stormwater Bond Funding to be used to build, repair, modernize, and improve drains, pipes, and other necessary parts of Raytown's stormwater system.

timeline

Project Timeline

Raytown-Timeline_20251008.jpg
KEY DATES | 2024-2026

DECEMBER 2024

Begin Final Design

SPRING-SUMMER 2025

Impacted Neighborhood Meetings

open house postcard.jpg

Click to enlarge

Green Valley Subdivision

Tuesday, March 18th, 2025

Time: 5:30 to 7 p.m.

Location:

Raytown Schools Wellness Center

10301 E State Rte 350

Raytown, MO 64138

FALL - WINTER 2025

  • Design Plans Completed - Oct/Nov 2025

  • Contractor Selection Begins - Dec 2025

SPRING 2026

Construction Begins

Eastside Industrial Area - has been designed and bid with Infrastructure Solutions, LLC selected to do the construction. Construction is anticipated to begin mid-March 2026 and is scheduled to be completed in the Fall 2026. The project will install new storm sewer infrastructure along Railroad Street from 64th to 65th,  and along 65th and Hadley Streets down to 66th Street.

Click to enlarge

Gregory Heights

Thursday, April 24th, 2025

Time: 5:30 to 7 p.m.

Location:

Raytown Schools Wellness Center

10301 E State Rte 350

Raytown, MO 64138

RaytownStormwaterBondProjects-postcard-20250624-EastsideIndustrial-Mayview-FINAL.jpg

Click to enlarge

Eastside Industrial & Mayview Addition 

Wednesday, July 16th, 2025

Time: 5:30 to 7 p.m.

Location:

Raytown Mid-Continent Public Library

6131 Raytown Road

Raytown, MO 64133

CONTACT

CONTACT US:
Let us know about flooding issues and be included in email updates. 

Email updates:
Use the form below to add your name/email for project updates.

City of Raytown - Stormwater Bond Projects

This website is for education purposes only.
Paid for by the City of Raytown.

© 2025 City of Raytown. Created by Shockey Consulting.

bottom of page